Project Leader: Project Dates: May 27, 2010 - September 20, 2010 Email Address:
Education/ outreach 1 day
Check steps 13
Check Dams 22
Drainage dips installed 2
Dirt moved 55 bags
This hitch we took on new trails and different types of projects. Despite a cruddy cough mid summer funk that hit the group, everyone took great care of themselves and performed at an amazing level. The projects consisted of lifting, carrying, and strategically placing many locust logs and bags of mineral soil! No one in this group needs a gym! We are getting svelte and strong the good old fashion way!
We started off our hitch in Big Fat Gap. This location has 4 trails that branch out from… you guessed it a “Big Fat” gap. Both sides of this gap are very steep and are washing out. We decided the best way to hold back the bank was with locust timber stairs. That way it will be easier for the public to walk up the hill, and the hill will become stabilized by the logs holding back the soil. This was a fun project for all and gave us something different to accomplish other than the typical brushing and digging drainage dips.
Alex came to visit the group from Boise and we attended a great event in Asheville! The Americas Great Outdoors listening sessions was an awesome opportunity for the group to get the word out about what we are doing, and for the group to hear about other great outdoor achievements and ideas that are happening in Western NC. We celebrated our half way point this week and everyone agrees that the time is flying! We have accomplished so much and it is excellent to see all the transformations we have put into Joyce Kilmer coming together.
The second half of the hitch was spent on the Stratton Bald trail. This is a fall line trail that is heavily eroded. One could mistake this trail as a stream bed! The best solution to this trail was to place many check dams to eventually build the trail soils back up. In a few days the trail really started to transform. We have started the reversal of some erosion that took many years to develop. This whole process will take a few years to fully restore, but eventually the soils will build and walking the trail will be more enjoyable.
There was a ton of signs of Russian Boars on this trail and they are really tearing things up! They have been grubbing the sides of the trail creating a nice trench down each side. We will have our hands full when we start the deberming in this area! We need to teach those boars how to dig trails their technique is all wrong!