Finger Lakes National Forest 2010

Project Leader: Scott Meyler Project Dates: June 1, 2010 - September 20, 2010 e-mail: smeyler@thesca.org

Finger Lakes 2010 Video

Final Report

Trail work Totals for the Finger Lakes National Forest 2010
May 31- September 20, 2010

Campsite facilities built- 1 moldering privy
Turnpikes Constructed (number)- 4
Turnpikes Constructed (feet)- 140
Culverts installed- 3
Gravel hauled to worksites- 10 yards
6x6’s hauled to worksites- 42
Rock retaining wall constructed (number)- 1
Rock retaining wall constructed (sq. feet)- 15 sq. ft.
Drain dips constructed- 25
Trail brushed and cleared- Approx. 5 miles
Boardwalk removed- 48 feet
New Trail constructed- Approx. 600 feet

During the 2010 Finger Lakes field season a remarkable quantity and variety of work was accomplished. Crew members gained experience in both basic trail maintenance (drain dips, brushing and clearing, and new trail construction) as well as more technical skills such as rock work and construction. Some highlights from the field season include:

• Construction of the ADA compliant self-moldering privy at Dunham shelter which tested the crew’s construction skills and creativity and ability to think on our feet.
• Construction of turnpikes complete with ten inch culverts in two feet of standing mud.
• Construction of a retaining wall on a steep hillside on the Ravine Trail.
• Construction of four trail re-routes along the Interloken Trail.
• Construction of approximately 25 drain dips on the Interloken and Burnt Hill trails.
• Brushing nearly 5 miles of trails, including ½ a mile of multi flora rose on the Backbone trail.

Hitch 8 report

Program Name: Finger Lakes National Forest
Dates: 9/7/10- 9/13/10

Finished self-moldering privy
South Burnt Hill pond Turnpikes- 2
Interloken drain dip- 1, 450 feet long
Decommissioned old privy
Broke down camp, washed car and tools

Hitch 8 wrapped up the field season for the Finger Lakes tails crew. It has been an incredible summer full of many challenges and accomplishments. Throughout the summer we built a stone retention wall on the Ravine trail, four re-routes along the Interloken trail, and many drain dips along the Interloken and Burnt Hill trails. During hitch 8 we put the finishing touches on the self-moldering privy we have been working on since Hitch 3, however, our main accomplishment this hitch was completing two turnpikes on the Interloken trail near the South Burnt Hill pond. Along with the two we built last hitch we used 34 6x6’s, over 170 feet of landscape fabric, and 10 yards of gravel. It certainly was a tall order when we started building the turnpikes last hitch, but with the help of the Forest Service and their ATV’s we were able to get them done with a few days to spare. After completing the turnpikes we focused our energies on a few little odd jobs, such as cleaning up a drain dip we built on the Interloken trail, and then started the long process of breaking down and cleaning up camp, our tools, and the truck.
The entire crew would like to thank the US Forest Service and the Forest Service employees at Finger Lakes National Forest. They made our stay here fun, informative, and productive. We also want to encourage you to come visit the beautiful Finger Lakes National Forest and see all our great work firsthand.

Marc cuts a hole in the privy floor for the toilet seat.
Kevin and Marc cut holes in the privy floor for the movable toilet seat.
Ellen spreads the gravel that Marc and Kevin haul to the turnpike.
Kevin unloads a wheelbarrow full of gravel.
Marc unloads his wheelbarrow so that he can go back for another.
Holly drives in rebar to stake down the 6x6.
Marc is happy to start filling the last of the turnpikes.
Kevin is happier to tamp the final turnpike.
Stuffed peppers, asparagus, and yellow squash for dinner tonight.
Scott demolishes the old privy at Dunham shelter.

Hitch 7 report

Progress Report:

Program Name: Finger Lakes National Forest
Dates: 8/23/10- 8/30/10

South Slope trail corridor- ¼ mile
Drainage ditch on Interloken- ¼ mile
Privy- Trim, roof, trail
Turnpikes- 4
Cleaned Rainbow camp- 15 garbage bags

During hitch 7 we finally started work on a project we have be prepping since hitch 1; building turnpikes on the Interloken trail. During hitch 6 we completed some of the prep-work for one of the turnpikes, digging culverts and laying in the 6x6’s. When we arrived back to work on the 23rd the gravel we needed to make the culverts was waiting for us. However, we had to wait a few days before we could get Marv and Rebecca’s help transporting the ATV and Mule to the work site. Rainy weather kept postponing our use of the ATV and Mule as well. To keep busy while we waited we dug a drain ditch along the Interloken trail near South Burnt Hill pond where two of our turnpikes will be installed. The drain dip, when all said and done, turned out to be ¼ mile long.
As well as digging drainages we put some finishing touches on the privy. We finished up the trim, the screening, and built a trail leading to the privy. While we were at the privy site we also restored the vista from the trail shelter by cutting down the undergrowth and sumac that had blocked the view. Lastly, on Friday we helped Marv clean up an abandoned campsite off the Backbone trail. The site was abandoned by the Rainbow group who left four tents, kitchen supplies, food, chairs, and garbage.
That afternoon, after cleaning up the campsite, Marv brought the ATV and the Mule to the turnpiking worksite and we started hauling gravel from the parking lot up the Interloken trail to the turnpike. For the next few days we hauled gravel to the four turnpiking sites and filled them in. By the end of hitch seven we completed two of the turnpikes and have the other two well underway.

Deserted Rainbow camp food tent.
Deserted Rainbow camp.
Deserted Rainbow camp kitchen sinks.
Deserted dishes.
Deserted produce.
Deserted kitchen.
Inside the deserted food tent.
Holly and Scott unload gravel from the ATV to use for turnpiking.
Kevin spreads gravel for the turnpiking.
Marc brings Kevin more gravel.
Holly spreads gravel for the turnpike crown.
Marc is very happy to be tamping down the gravel.
Kevin shows off by carrying two bags of gravel.
The first turnpike is complete.
First turnpike complete with 10" culverts.
The first hikers to use our newly constructed turnpike.

Hitch 6 report

Program Name: Finger Lakes National Forest
Dates: 8/9/10- 8/16/10

Culverts under Interloken turnpike- 3
Laid 6x6’s for Interloken turnpike- 12
Burnt Hill drain dips- 10
Installed carsonite posts- 5
Native Plant restoration- 900 plants

With the privy nearing completion we were able to focus our attention on our next big assignment, installing turnpikes along the Interloken, Gorge, and South Slope trails. Of the three the Interloken trail turnpike will be the biggest challenge. Since the trail is so low and muddy we started by installing 3 large culverts (two 10 inch and one 12 inch) underneath the future turnpike. The ground was so wet it nearly took our boots off with every step, and made digging the trenches for the culverts quite the challenge. However, as always, we persevered and by the end of the first day all 3 culverts were in the ground.
On the second day we took a break from the turnpiking to check out Empire Farm Days, the largest farm show in the Northeast. While at Farm Days we learned new techniques on breaking in horses, how to identify invasive insect pests, new farming methods, and even taste tested new products such as June berries and new strains of corn.
On day three it was back to work again. We helped Rebecca and four Green Mountain National Forest employees plant over 900 native plants at a site that was treated for the invasive Vinca, aka Periwinkle, plant last spring. The planting took the entire day. It was a nice change of pace to plant a native plant rather than to cut down and uproot an invasive plant. All summer long we have been removing invasive plants so it was good to finally put something in in their place.
On the fourth day of hitch it was back to the turnpike. We dug drainage ditches into and out of our culverts and laid the 6x6’s that will hold the turnpike in place. Like the culverts on day one the mud made it difficult to lay in the 6x6’s in place. It took a full day and the morning of day five to finish laying in the 12 6x6’s. After we finished laying in the 6x6’s and staking them in with rebar we headed up to the northern end of the forest were a tree had fallen across the Interloken trail. Scott was able to clear the tree with the chainsaw. They rest of the afternoon was spent installing carsonite posts at trail heads on the northern end of the forest.
On the morning of day six Marc, Holly, and Ellen moved a sign that was in the wrong place on the Interloken trail while Scott and Kevin scouted some boardwalk that needed work near Foster Pond. Afterwards we went to the Burnt Hill trail between Burnt Hill Road and the Interloken trail to build drain dips. We were able to finish 3 drain dips on day six, and finished off the last seven on day seven before heading to the South Slope trail to clear another downed tree.
As usual, we spent the last day of hitch cleaning tools, breaking down camp, and doing administrative work.

Ellen, Scott, and Marc dig trenches for culverts.
Marc clearing the trench he dug for a culvert.
Scott and Ellen continue work on the trenches for culverts.
Holly is a proud mud-warrior after a day of digging trenches on a wet part of the trail.
Holly fearlessly holds a hissing cockroach that was at Empire Farm Days
A display of the invasive species Asian Longhorn Beetle ravaging the forests of NY.
Kevin and Ellen catch some much needed breeze in the USDA tent at Empire Farm Days.
Kevin, Ellen and Marc plant native plants in an area where an invasive species had taken over and was removed.
Ah, fresh native plants to hopefully take root and reclaim this part of the forest.
Kevin digs a hole for a plant to take root.
Marc plants a native species in the once over-grown area
Holly baked Ellen a cake for her 23rd birthday using the ez-bake oven!
Holly begins work on the drainage system for the new turnpikes on Interloken trail.
Kevin also works on the drainage system for the new turnpikes.
Marc digs a trench for water escape from the culvert
clearly, this is where we were planning to place these.
Marc tamps down the mud where the gravel is to be laid.
Marc and Kevin move a large rock out of the way.
Marc notches a 6x6 to fit over a culvert.
Ellen cuts slats in the 6x6 to make the notching easier.
Ellen steadies the 6x6 so that Kevin can cut slats.
Marc notches the 6x6 that Ellen and Kevin prepped.
Holly and Ellen dig trenches for the last two 6x6's.
Holly and Ellen set the 6x6's in.
Marc tamps the future turnpike.
The crew hard at work on the turnpike.
Kevin is pumped that all the 6x6's are in.
With all the 6x6's laid in we are just waiting for gravel.

Hitch 5 report

Progress Report:

Program Name: Finger Lakes National Forest
Dates: 7/26/10- 8/2/10

Burnt Hill and Interloken Trail Corridor- 3.5 miles
Drilled pilot holes for rebar in 6x6’s- 32 6x6’s – 3 holes each
Interloken trail drain dips- 8
Privy Roof, Ramp, Trim, Door
Toured past worksites with Holly Knox and Rebecca Wright
Toured logging operation with Holly Knox and Rebecca Wright

We started hitch 5 by clearing 3½ miles of corridor on the Burnt Hill and Interloken Trails. The trails were in fairly good shape and were not overgrown too much so we were able to complete the 3½ miles in less than a day. After clearing the corridor Marc and Kevin went to work removing an old, rotten boardwalk while Holly and Ellen started drilling pilot holes in the 6x6’s we will be using for turnpiking. The battery powered drill was not powerful enough to drill through the pressure treated 6x6’s so Holly and Ellen had to resort to a brace and bit to get the job done. It was hard, slow work drilling the ¾ inch holes with a brace and bit but Holly and Ellen kept at it and three days later all the pilot holes were finished. While Holly and Ellen finished drilling holes Scott, Marc, and Kevin went back to the privy and finished the roof, walls, ramp, and door. The building is now complete, we are just waiting on accessories such as the toilet seat and grab bars and it will be ready to open.

After drilling holes and putting finishing touches on the privy we went to work digging drain dips along the Interloken Trail. The dips were especially challenging because they were on relatively flat and wet ground. We had to use our brains a bit in order to come up with drain dip designs that would work well. I was happy to see that the crew understands the concepts and theories behind drain dips and was able to apply them in order to build unique, yet effective drain dips.

During hitch 5 we were visited by Holly Knox from Green Mountain National Forest. On the morning of her visit we visited a timber sale taking place on the forest. Rebecca Wright gave us a tour of the timber sale and explained the science behind sustainable logging to us. It was a great learning experience as well as a fun adventure. Afterwords Scott took Holly and Rebecca on their own tour of our past, present, and future worksites and explained the science behind trail construction and maintenence. Holly and Rebecca were both impressed by the work we have accomplished thus far.

The battery-powered drill was no match for the pressure treated 6x6s so Ellen uses a brace and bit to work through the boards.
Holly drills through a 6x6 the old-fashioned way using a brace and bit.
Marc "The Destroyer" tears up hazardously decrepid boardwalk.
Scott begins work on a drain dip for Burnt Hill trail.
Marc shovels loose dirt from the drain dip on Burnt Hill trail.
The privy awaits it's roof.
Scott stands next to the privy with it's completed walls.
The roof starts to shape up.
The privy finally has a roof!
Marc in surprised that Holly was able to make such delicious wet burritos.
Kevin clears a drain ditch on the Interloken trail.
Classic road crew scene.
Drain dip on the Interloken trail.
Marc outslopes a section of the Interloken trail.

Hitch 4 report

Progress Report:

Program Name: Finger Lakes National Forest
Dates: 7/13/10- 7/20/10

Carried lumber to privy site
Stained Plywood- 17 4x8 sheets
Backfilled Interloken Trail with soil removed from privy foundation- 150 feet
Constructed Privy
Carried 6x6’s up Gorge Trail- 11 8 foot 6x6’s

The majority of hitch 4 was spent working on the moldering privy at Dunham Shelter on the Finger Lakes trail. The Finger Lakes trail is part of the North Country trail system, and the new privy will be a dramatic improvement for through hikers as well as casual day hikers and picnickers.
We started off the hitch by carrying the lumber we stained last hitch to the privy site. It was a big challenge and took Kevin, Ellen, and Marc the better part of the day, but would have been a lot harder if it wasn’t for Marv (a US Forest Service Employee) and his ATV. While Kevin, Ellen, and Marc carried in the lumber, Scott and Holly carried out the soil excavated from the foundation and put it to use building up some particularly muddy sections of the Interloken trail. On day two we focused on staining the remainder of the plywood for the privy. We sure were glad to finally finish staining this day. After letting the plywood dry overnight we hauled the plywood to the privy site. Again, thanks to Marv and his ATV. We then spent the afternoon constructing the framing for the floor of the privy.
On day four we took a break from constructing the privy. We could not go any further until the circular saw the USFS was nice enough to buy us came in. We spent the day carrying the remainder of the 6x6’s we will be using for turnpiking up the Gorge trail. Way back in hitch 1 we hauled 9 6x6’s up the trail, but still had 11 left over. While carrying in the 6x6’s it was obvious to us how much stronger we have gotten in the past 6 weeks. Back in hitch 1 it was incredibly difficult to get the 6x6’s up the trail. During hitch 4 we carried them in without even having to take rest breaks!
On day five our circular saw had arrived and we got back to work on our top priority, the moldering privy. By the end of the day we had the floor finished and all the walls framed off. The following day we hung the plywood walls up. Hanging the walls turned out to be harder than we anticipated; plywood is not light. Nevertheless, all four walls were complete by the end of the day.
On day seven we constructed the privy door. Afterwards we realized that there was not enough 2x4s to frame the roof. We spent the afternoon tracking down 2x4s and staining them. On the final day of hitch 4 we finished framing the roof. The privy is now 90% complete. We are just waiting for the roofing materials and the toilet accessories to come in and we will have it finished in no time.

Marc stains plywood for the privy.
Scott, Ellen, Kevin, and Marc staining plywood.
Holly supervises the crew.
Kevin cuts a 4x4 to length.
Scott secures the framing for the floor.
Scott holds a 2x4 in place so Marc can secure it.
Floor framing complete.
Ellen removes Purple Loosestrife growing at the USFS office.
Scott bags the Purple Loosestrife that Kevin and Ellen cut.
Kevin, excited to start schlepping.
Crossing the stream bed.
It got a bit tricky right here.
Adding to our growing pile of 6x6's.
Ellen tacks in screening to keep animals out of the privy.
Marc helps Kevin steady a board he's cutting for the privy.
Marc helps Ellen steady a board she's cutting for the privy.
Holly takes a measurement to be used on a 4x4.
Marc envisions what the walls will look like on the privy.
Holly screws a 2x4 into place.
Scott repairs a broken 4x4.
The crew admires their work during lunch.
Scott screws a wall into place.
Scott and Ellen observe Kevin as he screws a wall into place.
Scott and Kevin are all smiles over the completion of the privy walls.

Hitch 3 report

Progress Report:

Program Name: Finger Lakes National Forest
Dates: 6/28/10-7/2/10; 7/6/10-7/8/10

Carried 6x6’s for privy cribbing to worksite- 8 -12 foot 6x6’s
Dug foundation for moldering privy- 12x6x2 feet
Built cribbing
Interloken re-route #3- 153 feet
Interloken re-route #4- 200 feet
Stained lumber for privy
Cleared downed tree on Interloken trail

On our third hitch we started work on our top priority for the summer, constructing a new moldering privy at the Dunham Shelter on the Finger Lakes trail. We spent the first day hauling 6x6’s to the worksite before a thunderstorm sent us home early at 4:30. Starting on day 2 we dug out a foundation for the moldering privy and started working on the cribbing. It took a lot of concentration and patience to get the first 6x6’s level but once they were in place the rest of the cribbing was a breeze. After building the privy we focused on staining the lumber we will be using to construct the privy. It is amazing how much lumber it takes to construct this 6x12 building!
While Holly and Ellen were hard at work staining the lumber, Scott, Marc, and Kevin focused on constructing two new re-routes on the Interloken trail. During the holiday weekend there was a large trail running race throughout the National Forest. 250 runners ran races of 25K, 50K, and 50 miles throughout the forest, including the section of the Interloken that needed to be re-routed. We wanted to finish the re-routes before the race so the runners would not have to run through thick mud. We also cleared a downed tree on the Interloken trail that was blocking the trail and impeding the race.

Kevin lashes a 6x6 to a pick handle to be carried to the privy site.
The crew carries a 6x6 to the privy site.
Almost there!
Trying a new method.
It worked!
Kevin and Scott cut a 6x6 in half to be used on the cribbing.
Marc and Ellen after clearing the privy location.
Marc digs the foundation for the cribbing.
Scott digs out the foundation for the cribbing.
Leveling the foundation.
Finally level!
Interloken trail, before re-route.
Interloken re-route, before.
Marc clears the Interloken re-route.
Kevin digs the tred for the Interloken re-route.
Tree blocking the Interloken trail.
Scott clears the tree from the Interloken trail.
Kevin cuts a root out of the re-route.
Ellen clears the loose soil from the trail.
Holly clears the loose soil from the trail.
Interloken re-route, after.
The crew stains plywood for the privy.

Hitch 2 report

Progress Report:

Program Name: Finger Lakes National Forest
Dates: 6/14/10-6/21/10

Planted Tree at Hector Ranger’s Office (1 Dutch Elm’s Disease resistant Elm Tree)
Ravine Trail Drain Dips (4)
Re-established Ravine Trail Outslope and benching (260 feet)
Interloken Trail Drainage Structures (5)
Ravine Trail corridor (¾ mile)
Ravine Trail Retention Wall (30 square feet)
Brushed/Cleared/ removed multi flora rose Burnt Hill Trail (½ mile)
Interloken Trail reroutes (216 feet)

We started hitch 2 by planting a Dutch Elm’s Disease Elm tree at the USFS Ranger’s Office. Planting this tree gave us hope that the American Elm could possibly make a recovery in the future.
After planting the tree we got back to doing what we do best; trail work. We headed over to the Ravine Trail to take a look at a retaining wall Rebecca told us was falling over. When we got there we could not believe what we found. The wall was completely toppled over, and most of the rocks used to make it had slid more than 20 feet down the slope the hill was sitting on. We knew immediately we had our work cut out for us. The original was constructed by standing a few flat rocks vertically and pounding rebar in behind them to hold them up. The wall was built on a slope approaching 45 degrees. It was no wonder that the wall fell over backwards.
We started by benching the hill to construct a solid, flat platform to build the wall on. We then dry-stacked the local shale so as to create a much more solid wall than the original. We quarried stone from the creek bed at the bottom of the ravine trail. Resources were plentiful, but moving them up the tall, steep hill was a challenge. It took four days to finish the wall, but we left with an incredible sense of accomplishment.
We could only have three people working on the wall at a time because there was simply no room on the steep slope for any more than that. So when the two extras were not quarrying for materials we worked on some improvements on the Ravine trail. We brushed and cleared the entire ¾ mile loop, installed 4 drain dips, re-established 210 feet of out-slope, and benched 50 feet of trail.
After finishing up the Ravine trail we headed over the to Burnt Hill trail to clear out some multi flora rose that has been giving horse riders a problem. In addition to the rose thorns we had to work around the barbed wire fence they were growing along. This section of the Burnt Hill trail runs along one of the many cow pastures in Finger Lakes National Forest. While the crew cleared the multi flora rose, Scott went to the lumber yard with Marv to pick up materials for the privy we will begin constructing next hitch. The crew has cutting multi flora rose down to a science and finished nearly a half a mile of fence by the time Scott returned from the lumber yard. We quickly finished up the rest and packed it in for the day.
The next morning we went to headquarters and unloaded the privy materials from the trailer and put them inside the shed where they will be protected from the elements until we can build the privy. Afterwards we headed to the Interloken trail and finished the drainage structures we started last hitch. We could not complete them at the time because it rained for several days straight making the soil too muddy to dig in. The trail was still very muddy but we were able to make due. After finishing up the drainages we headed further up the Interloken and started the first of four re-routes on the trail. We cut the re-route corridor and finished 90 feet of tread before heading home.
On Sunday the 20th we took a break from trail work to volunteer at an archaeological dig in the forest. We spent the morning getting a tour of the site and learning a little bit about the history of the area. After the tour the archaeology students taught us how to dig a unit. Both Scott and Ellen had previous experience in archaeology and the rest of the crew picked it up quickly. Turns out trail workers are great diggers, who would of thunk it. Unfortunately we did not make any discoveries on this day. Around 2 o’clock the archaeologists headed over to the office to was and categorize artifacts so we went back to the Interloken trail to finish our re-route. We were just able to finish the last 60 feet of trail before thunder and lightning forced us to pack it up around 4:30.
On the last day of our second hitch we went back to the Ravine trail to finish up a small section that needed corridor work. Afterwards we headed back to the Interloken trail and cut the second re-route. We finished the 66 foot re-route just in time for lunch. After lunch we spent the rest of the day cleaning and sharpening our tools and reporting our hours to AmeriCorps.

Dutch Elm's Disease resistant Elm, planted at Hector District office
Ravine Trail retaining wall, before
Ellen, Marc, and Scott bench the slope to create a solid foundation for the wall
First level complete!
Kevin and Holly making crush to backfill the wall
Kevin bags up the crush he made
Holly carries the rock she quarried to the wall
Holly proud of her work
Marc and Ellen fit the next stone into place
Ravine Trail retaining wall after day 2
Scott and Marc moving the heaviest rock to the wall
Taking a breather...
now for the hard part
Ravine Trail retention wall after day 3
Kevin puts the finishing touches on the wall
Ravine Trail retention wall; after. What a great job we did!
Scott, using the chainsaw to remove a fallen tree from the Ravine Trail.
Look at Scott go!
All clear.
Holly, digging a drainage ditch on the Interloken Trail.
Kevin, digging a drainage ditch on the Interloken Trail.
A muddy Interloken Trail before we re-routed it.
Scott, re-routing the Interloken trail.
Holly and Marc, working to re-route the Interloken Trail.
The end result; a new and improved section of the Interloken Trail.
How pretty!
Kevin, working to re-route a section of the Interloken Trail.
Scott, observing a re-routed Interloken Trail.
Kevin excavates an achaeological site.
Marc and Ellen learn a little about the history of the site.
Scott helps field school student, Adriene, measure the depth of an excavated unit while Ellen learns the process.
Holly carefully excavates a unit.
Kevin reads off grid coordinates of artifacts.

Project Leader: Scott Meyler

Although I may be new to the SCA I am not new to conservation work and trail construction. From 2006-2009 I was Crew Chief for the Middlesex County Conservation Corps while studying Environmental Policy at Rutgers University in New Jersey. I directed the construction of ten new trails in parks throughout the county as well as maintenance of the existing trails. I also supervised habitat restoration projects, tree plantings, erosion control projects, invasive species removals, litter cleanups, and beach sweeps. In my three years as MCCC Crew Chief I trained more than 25 high school and college students and over 100 volunteers on proper trail construction and conservation techniques.

My close relationship with nature started early in life. As children my brothers and I spent our summers catching frogs, crayfish, snakes, and box turtles in the streams and ponds around our house. Family vacations usually consisted of camping, canoeing, biking, and hiking. While most kids dreamt of being astronauts or firefighters when they grew up I dreamt of being an explorer and photographer for “National Geographic.”

My thirst for adventure was finally quenched in 2006 when I had the fortune of spending a summer in Kenya on an archaeological dig sponsored by the Rutgers paleoanthropology department and the National Museum of Kenya. For eight amazing weeks we trekked through Kenya stopping to work at many famous archeological sites. I had the great fortune of uncovering the oldest anatomically modern footprints ever found, 1.5 million years old, and belonging to Homo erectus. Other discoveries included evidence of early stone tool butchery, and partial forearm and hand fossils.

I am excited by the opportunity to serve nature, and give back to the forests in which I enjoy spending much of my time. I hope that my work in the Finger Lakes National Forest inspires others to do the same. My goal is that visitors to the National Forest leave not only with a better understanding of the natural world around them, but also a better sense of themselves and how they fit into it. It is my pleasure to provide our visitors with exciting recreational opportunities as well as opportunities for personal growth and reflection.

Project Leader: Scott Meyler

Hitch 1 report

Progress Report:

Program Name: Finger Lakes National Forest
Dates: 5/31-6/9/2010

Brushed and cleared Interloken trail (2 miles)
Brushed and cleared Backbone trail (1 mile)
Brushed and cleared South Slope trail (.5 miles)
Brushed and cleared George trail (.25 miles)
Brushed and cleared Finger Lakes trail (.5 miles)
Installed Drain Dips (2)
Prepped turnpike materials
Cut rebar (70 pcs.), landscape fabric (140 feet)
Carried turnpike materials to worksite (20 6X6’s .5 miles)

We spent our first day setting up base camp, meeting the USFS staff, and scouting worksites. Rebecca Wright, our agency contact pointed out some trouble spots where horse users were complaining they could not get through the trail. We spent the first few days brushing and clearing these trouble spots on the Interloken and Backbone trails. Scott used the chainsaw to clear a large (14 inch) tree that had fallen across the north end of the Interloken trail blocking access to horseback riders. Both the north end of the Interloken trail and the Backbone trail were completely overgrown with multi-flora rose. We were all pretty scratched up by the rose thorns by the end, but we managed to cut back the multi flora rose off the trail.

After taking care of the trouble areas we moved on to one of our top priorities, the southern end of the Interloken trail to the Burnt Hill trail. The trail runs through mature forest so brushing and clearing the corridor was fairly easy. There wasn’t much underbrush like on the Backbone and the north end of the Interloken, and thankfully no multi flora rose. On Saturday the 5th of June we started building two uphill-side ditches to help dry up so very muddy areas on the Interloken trail. We have not finished them because it rained for the rest of the hitch and the soil became too muddy to work with.

We spent the rest of the hitch brushing and clearing the Southslope trail, the Gorge trail, and prepping turnpiking materials for future projects. The crew spent about a day and a half on the Southslope and Gorge trails. Scott left one afternoon to pick up 6X6’s for turnpiking. On the 7th and 8th day of the hitch we carried 20 6X6’s up the Gorge trail and the Interloken trail to our turnpiking sites. We had to do the half-mile trek 10 times to get all the 6X6’s in. It was hard work. We had to climb some pretty steep hills and navigate some narrow trails to get them in. Everybody was exhausted. We couldn’t even stay awake long enough to watch the sun go down on those nights.

Backbone Trail, before
Backbone Trail, after
Backbone Trail, before
Backbone Trail, after
Ellen hauls off the Multi Flora Rose she cut
Marc hauls away the Multi Flora Rose Holly cut
Kevin digs out a drainage ditch
Ellen and Holly carry a 6x6 to the worksite
Marc shows off his strength
For the longer treks we thought some handles would be nice
Scott shows Kevin how to lash the 6x6's together
Schlepping the 6x6's up the Gorge Trail
It got pretty tricky up the steep, narrow hills but we perservered
Hitch 1 accomplishments, Northern half of Finger Lakes National Forest
Hitch 1 accomplishments, Southern half of Finger Lakes National Forest

Ellen Berry

I am from Portsmouth, Ohio but I have resided in Columbus, Ohio for the past three years where I attended The Ohio State University. This past March I graduated Summa Cum Laude with a degree in History. Over the past several years I have devoted much of my time to my studies, but I also enjoyed spending time with friends and family, reading, working out, traveling, volunteering, working various part-time jobs, and hiking. It was my appreciation for the outdoors that led me to apply for a position with the Student Conservation Association. After researching the SCA I knew it was a place where I could volunteer my time wisely for something I believe in and gain valuable experience all while in the outdoors.

Ellen Berry

Kevin Hart

Kevin is participating in an SCA program for the second time, the first during the summer of 2008 maintaining trails and monitoring campsites in the Frank Church-River of No Return Wilderness in Idaho. He is passionate about conservation work and hopes to land a permanent job in one of this country’s many beautiful parks and forests. He graduated in 2009 with a B.S. in Natural Resources Management and is thrilled to apply this knowledge in the Finger Lakes National Forest. He is also passionate about photography and frequently carries his digital SLR into the forest with him.

Kevin Hart

Marc Sobota

My hometown is Grand Rapids, MI. I am a recent (2010) graduate of Aquinas College, a small liberal arts college in Grand Rapids. I achieved a Bachelor’s of Science degree in Geography and an Associates degree in Business Administration. I have been interested in the outdoors since childhood. My father is an outdoorsman and would often take me on hunting and fishing trips. While at Aquinas my interest in conservation came to a head through my education in environmental studies and geography. In the final semester at Aquinas I learned of the SCA and was immediately intrigued and excited by the opportunities they offered. I have never done trail work before, but I am excited to be working outdoors and impacting people’s outdoor experience through sustainable trail building.

Marc Sobota

Holly Perkins

I was born and raised in one of the most beautiful states in the U.S., West Virginia. As a child the outdoor recreation was endless, from fishing and hiking to kayaking. Growing up this way I naturally wanted to work on the forest, I could not imagine sitting behind a desk for the rest of my life. I’m currently a student at West Virginia University, studying Parks and Recreation. I heard about the SCA over a year ago through a friend who had been involved in the High School program. After checking it out online I knew the SCA was where I belonged. I feel fortunate to be here and I know it will only help be get ahead in my field of study.

Holly Perkins

Homepage

Sign Up for News & Stories

Donate Now ButtonFind an Internship Button

Finger Lakes National Forest 2010

SCA on the Web

FB Flickr Twitter YouTube tumblr Pinterest